One of the requirements that our client has is connecting of their existing ECC system with BI 4.0 which is first time ever they are going to use.
I need couple of questions to be put forward for giving them an over view of it can be done if yes what is the procedure to be followed and what are the prerequisists.
Have gone through some SAP posts and found that Crystal Reports Enterpirse has a direct connectivity with BI 4.0 through a middle ware for ERP System.However this is only for BEX and also if ECC version is above 6.0.
However if ECC has CR 2010 and their ECC system is version </= 6.0 what is the procedure to be followed. Also if the underlying data source is other than BW. A brief info will also help.